AFNHB : GREATER NOIDA PH – II (19 Dec 2014) |
1. The defect rectification work is being carried out by AFNHB through petty contractors & labourers, as the Main contractor has abandoned the site and entered into arbitration in 2013 at Delhi High Court. 2. During the ongoing DLP, the allottees have faced problems for rectification, as there is no contractor at site available to rectify the defects. The defect rectification is presently carried out by AFNHB on daily basis, as and when the complaints received through petty labourer’s and technical supervisors deputed at site. Since the DLP was coming to end in Nov 14, AFNHB requested the society and allottees in Nov 14 to forward a consolidated list of defects so that comprehensive defect rectification work could be carried out through single contract. The consolidated list of 32 Nos. flats have been received from society/individual allottees. The selection of suitable contractor for defect rectification is under process. A meeting is proposed between this contractor and architect shortly. The work order for defect rectification will be issued after the meeting and the work for defect rectification will be commence shortly. 3. Repairing of UPVC windows and door work is under progress through authorized vendor’s. 4. The proposal for external painting/white washing also has been forwarded to architect for recommendation and will be processed further after recommendation of architect. 5. Case for obtaining completion certificate from Greater Noida Authority is under process and is expected shortly. 6. The meeting between Greater Noida Authority & Society was held regarding the construction of road. Society has to follow-up/take up the case with Greater Noida Authority. If society is facing any problem to take up the case, then AFNHB will assist for the same. 7. External Electric work is completed and all the defects have been rectified. 8. Fire fighting system is functional. Society has to maintain the system and keep the water pressurized in the pipe line, which is not maintained by the Society. Society is advised to maintain the same. Servicing of the Diesel Operated Fire Pump is under process. 9. The society is advised to collect the maintenance fund from the allottees timely as substantial dues are pending of Electric bills w.e.f. Oct 14 (Rs.1.24 lacs). This pending amount of not paid electric due’s may result in disconnection. The AFNHB shall not be responsible for non-payment of dues or disconnection of electric supply. Sd/- (K Wali) Gp Capt PD (WKS) For Director General |