WEB UPDATE – (31 Oct 2014) AFNHB BHUBANESWAR PROJECT
1. Consequent to the slow progress at site, a meeting with the MD, Dr S P Singh of M/S Omaxe Infrastructure & Const. Ltd was arranged at this HQs on 01 Oct 14. The civil contractor had cited his difficulty to raise the desired finances for the project leading to delays.

2. In order to facilitate the progress on the special request of the Civil Contractor, the Board has facilitated additional financial support against the Guarantees in order to infuse the funds required to achieve the progress. However, due to the festive season in the last month, the contractor could not muster the required manpower and progress as desired. However, he has assured, that he will increase the resources by first week of Nov 14 and completely mobilize the site by mid Nov. D G is scheduled to visit the site by third week of Nov 14 to assess the progress and take further steps so as to accelerate the progress.

3. Next update would be uploaded after DG’s visit to the site on III rd week of Nov 14.