STATUS:
  • Refund of Amount : Letter dated 6 Jul 12 more...
  • Fresh dates for Registration of DU's are planned to be carried out from 06 Aug 12 to 10 Aug 12.
  • Notice : All Allottees of Bangalore Ph-III are requested to immediately contact Project Office (080-23470239/8088731211) and clear their Electricity Bills failing which the BESCOM authorities would disconnect the supply.
  • Taking over of Physical Possession of Dwelling Units : 20 Mar 12. more...
  • Registration of Dwelling Units - Execution of Sale Deeds : 09 Mar 12...more ....
  • Water and Electricity connections have been released. Water from BWSSB is available on site now. Electricity is also available for all areas. Handing Over of Common Areas, Lifts, Sub Stations and other facilities to Society is in progress and will be completed very shortly.(12 Dec 11)
  • Electricity to all Blocks has been made available.(02 Dec 11)
  • Water from Bangalore Water Supply Board us available at site.(Uploaded on 02 Dec 11)
  • Project nearing completion. Allottees are requested to contact Project Director for Handing Over/Taking Over.(Uploaded on 02 Dec 11)
  • 1. AFNHB Jalvayu Heights Bangalore Phase-III at Jalahalli was inagurated on (06 May 11) by Air Mshl JN Burma, AOA & Chairman, AFNHB. Besides Rear Admiral R Gaikwad NM, DG AFNHB, Project Director Wg Cdr RA Raghvan, Staff of AFNHB, Contractor, Architect and allottees were present during the occassion. The Chairman complimented DG AFNHB, the Project Director, the Contractor and all staff for having executed the Project.
  • 1. BESCOM is likely to provide electric supply to blocks A, E and F by 30 Jul 11. Towards this individual electric meters are being fitted. The charging of electric supply would be done once all the meters are being fitted. All the allottees of the said 03 bloks are to forwarded a demand draft for Rs.5118/- (Rupees Five Thousand one Hundred and eighteen only) in favour of 'Air Force Naval Housing Board Bangalore' payable at Bangalore immediately. The DD must be sent to AFNHB Project, HMT Main Road, Peenya Plantation, Bangalore-560013.
    2. Click here for list of allottees of the 03 blocks who have already submitted the said DD.
    3. Allottees of blocks B,C and D may also forward the DD.
    4. Further, every allottees is requested to pay Rs.75/- (Rupees Seventy Five only) by cash at site towards labour for installation of the meters.
  • Society Charges : letter dated 22 Jun 11 ...more ....
  • Handing over schedule for B,D and C Block and Issue of Possession Letter at Bangalore : 10 Jun 11. Click here for details..
  • Letter dated 29 Apr 11 to AFGIS and NGIF regarding Cost of Dwelling Unit. Click here for details..
  • Issue of Possession letter and handiang over of flats.
  • Latest photographs uploaded.
  • STP work in progress.
  • Allotment of Dwelling Unit and Parking Space. Draw result held on 25th and 26th Dec 10. more...
  • Postponement of VI Inst. from 8 Dec 10 to 8 Mar 11 : Letter dated 26 Nov 10.
  • Option for Car Parking Space : Letter dated 12 Aug 10.
  • Letter dated:16 Jun 10 : Update more ....
  •  
    Category
    AI
    AII
    AIII
    B
    Cost (in lacs)
           
    Configuration
    S+12/13
    S+12/13
    S+12/13
    G+13
    Super Area (Sq Ft)
    1870
    1575
    1270
    890
    No of DUs
    78
    65
    65
    52
    Please click on a Image below for Slide Show
    Elevation View
    Location Plan
    Sample Flat A-I



    Sample Flat B



    A-II & A-III

    A-III

    Prog Feb 12