Updates:

Update as on (08 Jul 15):
1. Subsequent to the final opportunity granted by the Board to the Contractor for improving the progress of works, the Contractor has initiated mobilization of resources including manpower and finances at site.

2. With the above, there is increased deployment of resources at site with average manpower deployment of about 80 – 100 and 50 – 70 at Meerut and Bhubaneswar Projects respectively. The Contractor has also paid off his liabilities to various vendors and placed orders for additional material which has now started arriving at site.

3. Based on the current trend we expect the sites to be fully mobilized by end July 2015. A visit by Director General, AFNHB to both the projects is planned during the month of July 2015 along with the Managing Director’s of the Contractor’s firm to take a stock of ongoing works.

4. The Board will continue to closely monitor the progress in both the projects and undertake all possible measures to ensure expeditious completion of the balance activities.

5. Next update will be promulgated in August 15.

News Paper clipping on Delhi-Meerut rapid Rail Project.(15 Jun 15) ... [Read more....]
Meerut and Dehradun Ph II Re-Open for Registration (22 May 15) ... [Read more....]
Meerut Updates (5 May 15) ... [Read more....]
Kind Attention : Meerut Allottees : Update as on 13 Mar 15 [Read more....]
Meerut: Web update as on 1 Mar 15 [Read more....]
Update on AFNHB Meerut Project (21 Jan 2015) [Read more....]
1. Subsequent to the update on 29 Sep 14, DG AFNHB and Principal Director Works visited Meerut site on 11 Nov 14. Dr. SP Singh MD of M/s OMAXE (Civil Contractor) and the Architect M/s Garg Associate were also present at site. The current progress was reviewed and the quantum of balance work assessed.

2. The Board’s deep anguish on the slow progress and the severe criticism from the allottees on the failed timelines were highlighted to the contractor. Dr. SP Singh MD of M/s OMAXE apprised that the delays were primarily due to severe financial constraints faced by the company. However he assured the DG that they are committed to complete the project at the earliest and will definitely increase the man power and resources at site by end of Nov 14. He assured the DG to complete the FOUR blocks (Officers Cat-2 nos & Airman/Sailors -02 nos) by Apr 15 so that AFNHB could start the phased handing over of completed blocks and balance work on 04 blocks would be parallelly completed by Nov 15.

3. Specific directions have been issued to the contractors, that by the month end of Nov 14, the man power at site should increase to 200 nos and by end of Dec 14 to 300 nos with sufficient materials and resources. Any failure to achieve the timelines will result in issuing of termination notice and carrying out the balance work at Risk & Cost to M/s Omaxe.

4. A bar chart to complete the balance work in a fixed time schedule was also prepared and handed over to the contractor for adherence. He was again cautioned that any failure on the progress at any stage will not be acceptable and the Board would without waiting any further, terminate the contract and carryout the balance work at his Risk & Cost since further delays were unacceptable.

5. The next meeting to review the progress at site would be held during first week of Dec 14 and all allottees will be updated accordingly. WEB UPDATE – : NOTICE : POSTPONEMENT OF INSTALLMENT DUE ON 28 NOV 14 :
The last and final installment is postponed and will be collected from all the allottees at the time of offer for possession of dwelling unit. The detailed letter will be sent to all the allottees shortly. No penal rate of interest by AFGIS for Projects construction in progress. (10 Oct 2014). [Read more....]
Waiver of Penal Rate of Interest on HBL due to revision of date of completion of AFNHB Schemes (31 Jul 14 ): read more ...
Revised date of Second Additional Instalment from 30 Sep 14 to 28 Nov 14 : Letter dated (30 Jul 14 ): read more ...
  • UPDATE MEERUT AFNHB PROJECT-23 JUL 14.[Read more...]
  • Regional Rapid Transit System (RRTS) from Delhi to Meerut (14 Jun 14). [Read more...]
  • Postpone of first additional Instalment from 30 Apr 14 to 16 Jun 14. read more...
  • Revised Instalment Schedule (10 Dec 13). read more...
  • Delhi Meerut Express Way Update (22 Nov 13). read more...
  • Last installment further postponed from 07 Aug 13 to 05 Dec 13 : Letter dated 17 Jul 13. more...
  • Last installment further postponed from 07 May 13 to 7 Aug 13 : Letter dated 02 Apr 13. more...
  • Last installment further postponed from 07 Jan 13 to 7 May 13:Letter dated 23 Nov 12. more...
  • Allottees Suggestions : Letter dated 09 Aug 12. more...
  • Registration Re-opened for AI and AII Category for Priority I to IV for few vacancies. Last date of Regn.15 Sep 12. more...
  • Draw result held on 23 Jul 12. more...
  • 8th Installment Postponed from 13 Aug 12 to 07 Jan 13 : Letter dated 05 Jul 12 more...
  • Registration extended from 30 Jun 12 to 7 Jul 12. more...
  • Additional covered parking for A-I Category : (18 Jun 12) more...
  • Meerut and Jaipur Ph-II Schemes Re-opened for Priority I to IV for few vacancies. Last date of Regn.30 Jun 12. more... (25 May 12)
  • Suggestions of Allottees: (18 Apr 12) more...
  • Sample Flat for AI and AII category were inaugurated on 7th and 8th May 11 and B1and BII category on 11 Jun 2011.

    Forwarding of Technical Brochure 2010 : Letter dated 14 Jul 10 more ....
    Master Plan Part-1 : Master Plan Part-2 : Master Plan Part-3 : Master Plan Part-4 : Master Plan Part-5 :
    Old Updates Bin
  • Page 3

    Text...

    Page 4

    Text...

    Page 5

    Text...

    Page 6

    Text...

    Instalment Plan

    TENTATIVE COST , AREA, ACCOMMODATION ENUMERATED BELOW:
    TYPE
    SUPER AREA (APPROX) IN SQ FT
    TENTATIVE COST (RS.IN LAKH )
    REGN. AMOUNT (IN RUPEES)

    ACCOMODATION

    OFFICERS :

    AI
    1630
    27.99/25.98
    1,01,000/-
    DRAWING/DINING, THREE BEDROOMS, THREE TOILETS, BALCONIES & KITCHEN
    AII
    1450
    24.81/23.11
    1,01,000/-

    DRAWING/DINING, THREE BEDROOMS, TWO TOILETS, BALCONIES & KITCHEN

    AIRMEN / SAILORS
    B-I
    1010
    16.10
    51,000/-
    DRAWING / DINING TWO BEDROOMS, TWO TOILETS, KITCHEN AND BALCONIES
    B-II
    810
    12.90
    51,000/-
    DRAWING/DINING, TWO BEDROOMS, TWO TOILETS, KITCHEN AND BALCONIES
     

    - PARKING, SERVICE TAX, VAT AND LONG TERM MAINTENANCE CHARGES EXTRA.
    - THE NUMBER OF DWELLING UNITS FOR EACH TYPE SHALL BE BASED ON ACTUAL DEMAND.

     

    Instalment Plan:(MRA, MRB, MRC and MRD)
    AI
    AII
    BI
    BII
    Due Date
    Regn
    1,01,000
    1,01,000
    51,000
    51,000
    31 Aug 09
    First
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    08 Dec 09
    Second
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    09 Mar 10
    Third
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    08 Oct 10
    Fourth
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    10 Dec 10
    Fifth
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    11 Mar 11
    Sixth
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    11 Aug 11
    Seventh
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    13 Feb 12
    Eighth
    1,88,000
    2,16,000
    1,74,000
    1,62,000
    05 Dec 13
    Ninth
    2,66,672
    2,63,982
    2,03,792
    1,95,012
    16 Jun 14
    Tenth (Tentative)
    3,80,000
    3,80,000
    3,80,000
    3,80,000
    To Be Intimated
    Balance plus LTMF/ Service Tax/ VAT/ Parking shall be intimated later depending on actual prior to handing over of the dwelling units.
    Instalment Plan:(MRE & MRF)
    A-I
    A-II
    Due Date
    Regn
    1,01,000
    1,01,000
    09 Jun 11
    First
    6,00,000
    5,00,000
    10 Jun 11
    Second
    6,00,000
    5,00,000
    09 Sep 11
    Third
    6,00,000
    5,00,000
    10 Jan 12
    Fourth
    6,00,000
    5,00,000
    30 Apr 12
    Fifth
    2,98,000
    3,81,000
    05 Dec 13
    Sixth
    2,66,672
    2,63,982
    16 Jun 14
    Seventh (Tentative)
    3,80,000
    3,80,000
    To Be Intimated
    Balance plus LTMF/ Service Tax/ VAT/ Parking shall be intimated later depending on actual prior to handing over of the dwelling units.

    Photos.

    Inaguration
    3D View
    Plan AI
    Plan AII
    Plan BI
    Plan BII

    Sample Flat A-II
















    RRTS

    Updates. 28 Aug 14
    Updates. 28 Aug 14
    Prog.2 Jun 15
























    Location

    Shatabdi Nagar, Sector 4B, Po. Partapur, Meerut. Adjacent to Ansals Panchvati Enclave.