BHUBANESWAR
Status (6 Aug 14):
  • BLOCK A–1
    Structure and brickwork is completed. Internal plaster work is completed upto 3rd floor. Electrical works is in progress upto 50% complete in Block A-1. Block progress is 62.43%.
    BLOCK A–2
    Structure work and brickwork completed. Internal plaster completed up to 8th floor. Block progress is 65.03%.
    BLOCK A–3
    OHT slab casting 50% completed. Electrical conduit and PH work completed. Internal plastering up to 7th floor completed. Block progress is 61%.
    BLOCK A–4
    Structure up to 7th floor and brickwork up to 1st floor completed. 8th floor column shuttering and reinforcement is in progress. Block progress is 48%.
  • BLOCK B–1
    Structure up to 9th floor 50% completed. Brickwork upto 3rd floor completed. Block progress is 47.91%.
    BLOCK B-2
    Structure up to 4th floor completed. 5th floor column casting 65% completed. Block progress is 31.29%.
    BLOCK B - 3
    Structure and brickwork completed. Internal plastering completed upto 11th floor. Block progress is 75.21%.
    COMMUNITY CENTER
    External plaster is 95% completed. Painting, plumbing and flooring is in progress. 87% progress is achieved till date. In the past few weeks, the progress on the site has suffered due to inadequate resources and inadequate man power deployed by contractor. The contractor has been citing financial crisis. Consequently the Board has issued the Show Cause notice to the contractor and warned to cancel the contract and carry out the work by third agency at his risk and cost. However, recently the civil contractor has approached the Board seeking mobilization advance against Bank Guarantees in order to infuse funds in the project and achieve the desired progress. The Board has facilitated this and we expect the work to pick up and progress satisfactorily. Please be assured that the board will not spare any efforts at closely monitoring the work and ensuring that work progress at brisk pace to make up for lost time.
  • Payment Schedule (Fourth and Fifth Installment):Letter dated 10 Oct 13. ... Read more...
  • Sample flat Photos uploaded on this page. For Slide show pl. click on a snap and continue..
  • Kind Attension:Allottees Suggestions. Read more...
  • Sample flat meeting is planned at 1030hrs on 20 Apr 13. Read more...
  • Revised schedule of installment : 19 Oct 11. more...
  • 1. The Hon'ble High Court of Orissa While desposing Misc. Application No. 11310/11 in W.P. No. 19862/11 on 03 Aug 11 has passed the following direction:
    " Any allotment of Dwelling Units in respect of serving personnel of Air Force and Navy under AFNHB, Bhubaneshwar Scheme shall be subject to the result of the Writ Petition and also allotment shall be made keeping in view the reserved quota of retired employees."
    2. Reply in the case has been filed by the Board and the case is pending for final hearing.
    : Archive :
    Click here for site location on Wikimapia.
    SITE LAYOUT PLAN
    TENTATIVE COST, AREA AND ACCOMMODATION
    Type
    Super Area (Tentative)
    No of DU
    Tentative Cost (Lacs) Tentative Accommodation
    Officers (Type A) 1506 Sq Ft
    128
    30.16*
    Drawing/Dining Room, 3 Bedrooms, Kitchen, 2 Toilets, Utility and Balcony.
    Airmen/ Sailors (Type B)
    1155 Sq Ft
    128
    23.13*
    Drawing/Dining Room, 2 Bedrooms, Kitchen, 2 Toilets, and Balconies.
    * Post award of civil contract.
    INSTALMENT PLAN (Rs.)
    Instalment
    Category
    Due Date
     
    A
    B
     
    Registration Fee
    1,01,000
    51,000
    10 Dec 2010
    I
    4,50,000
    3,50,000
    08 Aug 2011
    II
    4,50,000
    3,50,000
    10 Jan 2012
    III
    4,50,000
    3,50,000
    10 Apr 2012
    IV
    4,50,000
    3,50,000
    07 Jan 2014
    V
    4,50,000
    3,50,000
    07 May 2014
    Will be intimated separately
    Google Image
    Site Plan
    Floor Plan_Offr

    Floor Plan_Others

    Community Centre
    Inaguration







    Prog.1 Mar 13





    Sample Flat Inag.






















    Progress as on 07 Jun 13







    Prog.6 Aug 13







    Prog.1 Sep 13







    Prog.5 Oct 13







    Prog.21 Oct 13







    Prog. 5 Nov 13







    Prog.18 Nov 13







    Prog.17 Dec 13







    Prog.4 Jan 14







    Prog.3 Feb 14







    Prog.4 Mar 14







    Prog.5 Apr 14







    Prog.3 May 14







    Prog.7 Jun 14







    COP Visit